personally it is the bored piles with cappingbeam and lagging wall. 3`?7<YJ
the main reason for this collapse may be the shortage of bending moment resistance of the wall. the surrounding building is the critical origin of the large lateral force. T<>,lQs(a
from the photo it can be seen that the site soil is not so bad. Pm?KI<TH~
measures may be : soil nailing between the piles to increase the wholly stability of the wall; E=Bf1/c\
increase the embedment (if the collapse came from overturning of the wall); prop up the wall with berms or inclined wall; or tie back from the back of the wall; G_tCmu\
meanwhile, monitoring should be carried out very carefully.